Mass Timber Fire Testing

Partners

Arup
KPFF Consulting Engineers
StructureCraft
Walsh Construction Co.

The mass timber components used to build Framework were the first in the world to pass two-hour fire tests demonstrating their safety for high-rise construction. Because the design is over 85', the team had to demonstrate that the structural components could resist a fire for two hours without losing their load-bearing capacity. This standard code requirement for high-rises gives occupants enough time to evacuate in the event of a fire and allow fire department intervention.

Cross-Laminated Timber (CLT) and other mass timber products perform well in a fire because of their monolithic size. During a fire, mass timber building components develop an insulating char layer at a predictable rate, allowing retention of structural integrity much longer than traditional stick-frame construction. A primary concern for the project's Fire Engineer was ensuring that the steel connections between columns and beams would remain structurally sound when exposed to fire for two hours. The successful completion of the 2-hr ASTM E119 fire tests exceeded this goal.

Clt fire testing at texas facility 900 0x398x2988x3735 q85

Mass timber column-to-beam connection being placed in a furnace and loaded with 25,000 lbs of pressure for testing.

2 hour fire test at texas test facility 900 0x126x3024x3780 q85
Framework column beam 1280 0x97x3528x2351 q85

Mass Timber Beam-to-Column Assembly

The custom glulam beam-to-column connection developed for Framework received the first two-hour fire rating in the world.

 

 

Slideshow close Slideshow arrow black Slideshow arrow black

Mass timber column-to-beam connection being placed in a furnace and loaded with 25,000 lbs of pressure for testing.

Mass Timber Beam-to-Column Assembly